See our previous post from June 2026.
You can see all the current and planned schemes on a map here.
Darnall-Attercliffe-City Centre
Work continues on adding a cycle track to Furnival Road, crossing Derek Dooley Way. The cycle track looks near completion on Effingham Street. There is a continuous crossing over Sussex Street which will improve safety for pedestrians and people on bikes.



Work also continues on Attercliffe Road, now adding a cycle track in the southbound direction.


Magna-Tinsley
The cycle track along Sheffield Road linking Blackburn Meadows Way is now complete. See the full scheme in 360 on Mapillary.

Work has started at the junction to the north of Meadowhall shopping centre to simplify the crossings.

City Centre
The pedestrianisation of Surrey Street is nearly complete, work has resumed on pedestrianising the last few metres.

The pedestrianisation of Pinstone Stone continues.

The upgrade to the rest of Pinstone Street is in progress. This will become a two-way street for bicycles while remaining a one-way street for motor vehicles.


Work continues on Arundel Gate and Charles Street, the primary focus seems to be adding the roundabout to Arundel Gate to make it easier for motorists to avoid the bus gate, although they are adding the new cycle tracks on Arundel Gate now.


Castle Street
Work has started on removing the central reservation from Waingate, which is the first part of the scheme.

Nether Edge – City Centre
Work has started in the city centre, expanding the cycle tracks along Moore Street and Charter Row.



The work in the Nether Edge area is expected to start in 2028.
Townhead Street and Leopold Street
No news.
Burngreave
No news.